Pacnet

Client

Pacnet

Location

Project Duration

15 weeks

Projects Size

4,350sqm

Status

FDC Mechanical Services and Technologies completed the data centre conversion for Pacnet in 2011.

The project included:

  • Conversion of three office levels to data centre use
  • Removal of redundant base building plant
  • Installation of air cooled chillers and infrastructure
  • Dual feed power with back-up generator

The project won the 2011 MBA (NSW) Award for Best Communication Building.

 

Awards

2011 Winner, MBA (NSW), Best Communication Building